BULFORD DOLPHIN
2001
• Installation and
Commission of Anchor Winch Control and Emergency Quick Release
System.
• Installation and
Commissioning of forced Ventilation Cooling System on Main
Switchboard.
BREDFORD DOLPHIN 2001
• Installation and
Commissioning of 155Kw Emergency Fire Pump, Control Panel
and associated control cabling.
• Re-wire of Power
and Control cabling of 2 No. Alimack Lifts.
• Installation and
Commissioning of Derrick Exd Occular Camera CCTV System.
• Installation of Akusta
Echo 8 Drillers Talk Back System.
BREDFORD DOLPHIN 2002
• Installation and
Commissioning of all Power and Control cabling for new Hydraulic
Pressure Unit.
• Installation and
Commission of Anchor Winch Dual Band Brake Control and Emergency
Quick Release System.
• Installation of all
small power, lighting and fire detection on Accommodation
Upgrade.
BORGHOLM
DOLPHIN 2002
• Main 600Vac Switchboard
and 750Vdc SCR Electromechanical Refurbishment.
• Installation of 440Vac
Distribution System.
• Installation of 110Vac
Distribution System.
• Installation and
Commissioning of Enwa RO Unit and associated Alarms.
• Installation and
Commission of Power and control cabling for Sewage Treatment
Plant and associated Alarms.
• Upgrade of PFEER
Public Address System.
• Installation of Power
and Control cabling for Air Conditioning Units.
• Installation of new
Compressor and Evaporator Units.
• Complete Det Norske
Veritas (DnV) defects list and close out.
BORGSTEN DOLPHIN 2002
• Installation of cabling
for Main Engine Alarms and Control Desk.
• Installation and
commissioning of Supply and Control cabling for Main Switchroom
HVAC System.
BULFORD DOLPHIN 2003
• Installation and
commissioning of all Power and Control cabling and Control
Panels for 3 No. Brandt Shale Shakers.
• Installation and
commissioning of all Power and Control cabling for 2 No. Swaco
518 Centrifuges.
• Installation and
Commissioning of Enwa RO Unit and associated Alarms.
• Installation and
Commissioning of all Power and Control cabling and Manufacture
Control Panels for complete Rig HVAC System.
• Manufacture, Installation
and Commission of 2 No. 55Kw Compressor Panels.
• Installation and
Commission of Drill Floor Stabbing Platform.
• Installation of all
DC Power and control cabling for re-instatement of Rotary
Table and auxiliary equipment.
• Installation of Akusta
Echo 16 Drillers Talk Back System.
• Installation of UPS
System for Gas Panel and Ballast Control Panel.
• Exd repair on 750Vdc
Drawworks motor power cables.
• Upgrade of Gas Panel,
Installation and Calibration of additional detectors.
• Emergency Switchboard
Cleaning, Torque, Insulation Resistance and Flash Test.
• Installation of Engine
Flow Line Metering System.
• Complete Insulation
Resistance testing of all ac and dc Motors.
• Complete Battery
autonomy discharge testing.
• Upgrade Battery Backup
Emergency Lighting.
• Complete Det Norske
Veritas (DnV) comprehensive defects list and close out.
BORGNY
DOLPHIN 2003
• Installation of all
Power and Control Cabling for additional National 12-P-160
Mud Pump and 150HP Supercharge Pump.
• Installation and
commissioning of all Power and Control cabling and Control
Panels for 3 No. Brandtl Shale Shakers.
• Installation and
commissioning of all Power and Control cabling for 2 No. Swaco
518 Centrifuges.
• Installation and
Commissioning of Power and Control cabling for 3 No. Enwa
RO Units and associated Alarms.
• Installation and
Commissioning of all Power and Control cabling and Manufacture
Control Panels for complete Rig HVAC System.
• Disconnection and
Re-Instatement of 4 No. Main Engine Alternators.
• Installation of Engine
Flow Line Metering System.
• Upgrade of PFEER
Public Address System.
• Installation of additional
Fire and Gas Detection.
• Installation of Crane
Boom Nav Aids and Flood Lighting.
• Installation of Power
Factor Unit Trips on ESD Level 2.
• Complete Battery
autonomy discharge testing.
• Upgrade Battery Backup
Emergency Lighting.
• Complete Det Norske
Veritas (DnV) comprehensive defects list and close out.